English (United States)

Norfolk-Stanton North Project

A final line route for the Norfolk-Stanton North Power Project’s new 115 kV transmission line was announced on January 23, 2024. Directly impacted landowners were sent a letter with a map of the final route, and all original property owners were mailed a newsletter. The project is now in phase 3, in which NPPD representatives work with property owners along the route on the project’s next steps.  

Thank you to the landowners for working with us during the easement acquisition phase and now as we begin the construction phase of the project. Right-of-Way (ROW) agents Neal Dreifurst and Andrew Jarecki will continue to communicate with landowners throughout the construction process.  

NPPD contracted Norfolk Tree Care, LLC of Norfolk, Nebraska to complete the tree clearing activities. Tree clearing activities will occur only in areas where easements and tree agreements have been obtained. Construction is scheduled to begin in June 2025. NPPD’s construction crew will be constructing the new line with support on the foundation work from Dietzel Enterprises, Inc. of Valley, Nebraska.

The need for this project is based on the area’s rapid growth and the current transmission system’s high electrical demand. The new 115 kV transmission line will increase the transmission system's capacity to meet increasing demand and further enhance reliability and resiliency in the surrounding area. This project fulfills NPPD’s obligation to serve wholesale customer demand.

Routes for a transmission project are typically developed over the course of several phases and are then narrowed down to a final route. 

  • In the first phase, preliminary route segments were determined. Next, the project team determined a preferred route along with alternative routes. The preferred route, which was selected based on engineering, environmental, and cost constraints, provides the most feasible path forward for design and construction. An open house was held for landowners and interested parties to provide input, including property information, and to learn more about the project.  
  • In the second phase of the public involvement process, NPPD determined a proposed route and presented it to directly impacted landowners at public hearings. The final line route was announced thirty days after the public hearings. 

Meeting Materials

Project Area Map

Newsletter

Meeting Materials

Project Area Map

Norfolk to Stanton Project Schedule - Phase 2

Questions? Email norfolk-stantonnorth@nppd.com or call 1-888-677-3412.